Route 10 (Route 1 to I-95) Widening

Revenue Sharing funds (50% state funds and 50% county funds), federal Regional Surface Transportation Program (RSTP) funds, and local funds will be used to widen Route 10 to six lanes between Route 1 and I-95. A Design Public Hearing was held on December 15, 2015. The major design features were approved on November 6, 2016. Right-of-way acquisition and utility relocations are complete. Branscome Inc. was awarded the construction contract. Construction began October 14, 2019 and completion is anticipated in Fall 2020.

Traffic Impacts

See Traffic Engineering Analysis Report and Access Management Waiver (PDF).

Project Timeline

Construction was completed on December 4, 2020.  

Contact

Stan Newcomb
Phone: 804-748-1037